Revised – 2025.12.23

TABLE OF CONTENTS – CHAPTER 08 – SURVEYS
800 – SURVEYS

800 – SURVEYS:

800.1 – General Requirements:

A. General:

1. This Chapter covers the Project Team procedures and accuracy requirements for survey services for site and/or Project layout and field measurement quantities determined by surveys.

2. Prior to beginning any field survey Work, the Project Team shall meet with the Project Representative to coordinate survey and reporting requirements.

B. Notice of Survey:

1. Before commencing any site and/or Project layout and surveys, the Project Team shall give the Project Representative 48 hours written advance notice so the Project Representative and/or GIS Services may witness such Work.

a. Refer to Part IV – Regulatory Requirements for utility locate requirements.

C. Field Measurements:

1. The Consultant is responsible for performing Field Measurements to verify existing conditions unless this activity is specifically excluded from the Consultant’s Scope of Work by the Project Representative.

D. Field Measurements typically require but are not limited to the following:

1. As–Built Measurements of Vertical Work:

a. Provide field verification of measurements and elevations of existing facilities to verify and or create accurate As–Built Drawings to be used for Project base data.

b. These measurements may be completed using modern technological equipment of the time to acquire the most accurate data for the survey.

2. Field Verification of Horizontal Work:

a. As–built measurement for items that shall be hidden or visible including all civil, mechanical, electrical, control Work and all utilities that are placed in concrete, earth or behind walls shall be made by and under the direction of a Colorado licensed surveyor while the Work is exposed and the measurements submitted to the Project Representative.

b. Unless noted otherwise the measurements shall show the final location within +/– 1 inch (or as close to as possible based on a specific situation that would limit the Project Team due to safety issues of the Project and/or site) of their actual vertical and horizontal location based upon NAD83 Colorado State Planes – North Zone – US Foot and NGVD 29 elevation.

c. Items located within 5 feet of a building shall be referenced to edge building foundation and building column lines and finish floor elevations and noted as such.

d. Special attention shall be paid to items requiring service, sensors, items with moving parts, access points and locations of junctions, elevation changes and directional changes.

e. Survey notes must be supplied to the Project Representative prior to covering up the Work or the Work shall be considered defective.

3. Data Format:

a. All data for the survey shall be provided in both digital form (current version of AutoCAD) and hardcopies to the Project Representative, GIS Services contact, the Facilities Management (FM) Survey Tech and FM Utility personnel.

b. Consultant must contact the Project Representative for a list for these persons.

c. Work shall be considered incomplete if data is not provided to all the required personnel.

800.2 – Site Work Surveys:

A. Control Points:

1. The Project Team shall locate at the Project/Work site all control points shown on the Construction Drawings by coordinates and/or elevation.

2. The Project Team must accurately survey control information to the points of application to ensure that all elements of the Work are correctly located.

B. Reference Location:

1. Requests by the Project Team to relocate survey reference/control points must be made 96 hours to the Project Representative prior to when the point shall be disturbed.

2. The Project Team shall replace/relocate at no charge to the Project any survey reference point(s) disturbed by Project Team and/or other within three normal working days after request has been approved.

3. Any Work which the Project Team begins before reference points have been provided, may be rejected.

4. Should the original reference points be obliterated or dislodged by operations which the Project Team controls, the Project Team shall replace them at no charge to the Project for the re–survey.

800.3 – Project–Specific Control Markers:

A. General:

1. Throughout the Project site one or more project–specific land survey control markers shall be provided. If these Project–specific control markers, monuments or benchmarks must be moved to accommodate the Project Team’s Work, the Project Representative must be notified with written notice 96 hours prior to when the benchmark or monument must be moved.

a. The Project Team shall do so at no expense to the Project.

2. If the Project Team destroys or obliterates any such monument or benchmark before contacting the Project Representative, the Project Team must notify the Project Representative immediately in writing and shall be required to pay the Project for all labor, materials, and equipment costs as assessed by the Project Representative for the replacement.

800.4 – Permanent Control Markers:

A. General:

1. Throughout the Project site there exists a System of monuments, benchmarks, reference and control points.

a. The Project Team is required to protect and preserve all of these survey references within the Colorado State University (CSU) Grid Control System.

2. Coordinates shown on the Drawings are based upon the CSU Coordinate System unless noted otherwise.

3. If any element of the University Land Survey Control System must be moved to accommodate the Project Team’s Work, the Project Representative must be notified with written notice 96 hours prior to when the reference or coordinate points must be moved.

B. Damaged or Destroyed Points:

1. Report damaged or destroyed reference points, CSU grid coordinate points and benchmarks to the Project Representative, GIS Services and FM Survey Tech.

2. The Project Representative shall reestablish damaged, moved, altered, or destroyed reference bench marks and coordinate points.

3. If reference, coordinate points, or benchmarks are damaged, moved, altered, or destroyed by Project Team, the Project’s cost of reestablishing such points shall be borne by the Project Team.

4. The Project Representative shall not be responsible for any increased costs or delays to the Project Team relating to reference points, CSU grid control points, or benchmarks which are damaged, moved, altered, or destroyed by Project Team or Project Subcontractors, suppliers, agents, or employees or other Project Teams working on the site.

C. Errors:

1. Report promptly alleged errors in reference points, CSU grid control points, or benchmarks to the Project Representative, GIS Service Tech and FM Survey Tech.

2. Discontinue use of reference points, CSU grid control points, or benchmarks alleged to be in error until accuracy of points can be verified or as directed.

3. Claims for extra compensation for alteration or recon­struction allegedly due to errors in reference points, CSU grid control points, or benchmarks shall not be allowed unless original reference points CSU grid points and bench marks still exist or substantiating evidence proving error is furnished by Project Team, and unless Project Team has reported such errors to the Project Representative as specified herein before.

D.  The following are limitations and additional information on reference point, CSU grid control points, and benchmarks.

1. The use of Control Monuments for construction surveying, other than those shown on the Construction Drawings or furnished by or accepted by the Project Representative is prohibited. Use of other monuments is at the Project Team’s sole risk and not recommended.

2. Elevations for main campus and surrounding areas are based upon mean sea level datum from NOAA–NGS benchmark “CSU2” elevation 5271.518 feet and must be verified by the Project Team prior to survey.

3. The CSU benchmark and coordinate point data as listed on the Construction Drawings or listed in the specification are the only approved coordinate points and benchmarks for construction surveying.

4. The basis of bearing of the Grid System is NGS control points geo–referenced per the North American Datum of 1983, Colorado State Plane, North Zone, US Foot Datum.

800.5 – Construction Lines and Grades:

A. Reference Points:

1. CSU Reference Drawings with benchmarks shall be provided by CSU for reference only.

2. Other control points and benchmarks may be provided to the Project Team at the discretion of the Project Representative.

B. Preservation of Points:

1. The Project Team shall carefully preserve such points and shall be held responsible therefor.

a. If it becomes necessary for the Project Team to remove or disturb a reference point or benchmark the Project Team shall notify the Project Representative before removing or disturbing said point.

2. If, in the opinion of the Project Representative, stakes, monuments, marks or points are carelessly or willfully disturbed by the Project Team, the cost of replacing such stakes, monuments, marks or points shall be charged to the Project Team and shall be deducted from payment for the Work.

C. Project Team Surveys:

1. The Project Team shall make surveys and layouts, as necessary, to delineate the Work.

a. The Project Team shall make the surveys for the proper performance of the Work.

2. As a part of such surveys, the Project Team shall furnish, establish and maintain in good order survey control points which may be required for the completion of the Project Team’s Work, subject to the acceptance of the Project Representative as to their location, sufficiency and adequacy.

a. Such acceptance by the Project Representative shall not relieve the Project Team of his responsibility for the accuracy of his survey Work.

3. The Project Team shall be responsible for any lines, grades, or measurements which do not comply with specified or proper tolerances, or which are otherwise defective, and for any resultant defects in the Work.

4. The Project Team shall be required to conduct re–surveys or check surveys to correct errors indicated by review of the field notebooks.

D. Quality Assurance:

1. The Project Representative shall have the right to check surveys and layouts made by the Project Team prior to accepting any of the Work.

2. The Project Team shall give advance notice of not less than 48 hours to the Project Representative to enable such checking prior to placing any Work.

3. The Project Team shall furnish assistance as may be required for checking purposes when so requested by the Project Representative.

4. The Project Representative may draw the Project Team’s attention to errors or omissions in lines or grades, but the failure to point out such errors or omissions shall not give the Project Team any right or claim nor shall in any way relieve the Project Team of their obligations according to the terms of the Project Team’s Agreement.

E. Quality Control:

1. The Project Team shall furnish skilled labor, instrument platforms, ladders and such other temporary structures, as may be necessary for making and maintaining points and lines in connection with the surveys required.

2. The Project Team’s instruments and other survey equipment shall be accurate, suitable for the surveys required in accordance with recognized professional standards, and in proper condition and adjustment at all times.

3. Surveys shall be performed under the direct supervi­sion of a Colorado licensed surveyor.

F. Field Notes:

1. The Project Team shall record surveys in field notebooks.

2. Copies of the original pages of such records shall be furnished to the Project Representative at intervals required by the Project Representative.

3. Each field notebook shall be furnished to the Project Representative when filled or completed.

4. Field notes shall be kept in the form and style shown of current and approved surveying theory and practices and based on per highest accuracy of understanding and professionalism of most current surveying procedures.

5. All electronic data collection and field notes and AutoCAD files of the survey must be provided to the Project Representative, GIS Service Tech and FM Survey Tech on CD or DVD.

a. The data shall be in MS Word and/or similar format and may be used to supplement field books.

6. Whichever method of note taking the Project Team starts with, it must use the same method throughout the Agreement duration.

7. If the Project Representative finds errors in the field notes they shall return them to the Project Team for correction and resubmission.

a. This review does not relieve the Project Team from the responsibility of maintaining accurate survey data.

800.6 – Larimer County Control Monuments:

A. General:

1. Verify control monument values with CSU Facilities GIS Services prior to survey.


STATION
DESIGNATION

NAD 83/92
LATITUDE

NAD 83/92
LONGITUDE

ORTHO
HEIGHT (M)

ELLIPS.
HEIGHT (M)

ORDER

30508

40º24’54.24463″ N

105º15’01.72114″ W

1691.16

1676.25

B

31503

40º25’55.16667″ N

105º20’23.85075″ W

1878.353

1864.436

C1

32908

40º45’54.43897″ N

105º29’12.31258″ W

2411.084

2398.675

C1

36 RMB

40º52’12.77927″ N

105º01’09.98237″ W

1736.318

1720.711

C1

56 RMB

40º46’20.04060″ N

105º20’26.89750″ W

1925.279

1911.800

C1

“A”

40º33’40.24373″ N

105º09’05.97681″ W

1757.646

1742.346

C1

A 409

40º29’30.80498″ N

105º04’37.72739″ W

1536.021

1519.930

C1

A 77

40º59’52.39735″ N

105º24’43.22543″ W

2298.816

2286.41

B

Allen

40º16’41.59290″ N

105º21’40.20722″ W

2021.76

2007.47

B

Azari

40º29’38.87965″ N

105º06’57.95290″ W

1566.014

1550.221

C1

B 135

40º42’03.75660″ N

105º33’45.56353″ W

2164.74

2152.64

B

B 137 Reset

40º43’11.40012″ N

105º10’19.94409″ W

1671.87

1656.98

B

B 357

40º40’07.24660″ N

105º04’09.71538″ W

1583.23

1567.52

B

Bartling

40º19’42.26304″ N

105º34’40.59657″ W

2516.596

2504.402

C1

Biggi

40º44’49.29418″ N

105º22’14.94338″ W

2053.22

2039.81

B

Blue

40º17’05.93092″ N

105º16’50.64647″ W

1742.512

1727.512

C1

BNSF

40º25’48.38728″ N

105º04’54.98186″ W

1531.01

1514.75

B

Bradshaw

40º35’04.09139′ N

105º02’08.32027″ W

1500.4

1484.12

B

Bud

40º37’22.72303″ N

105º00’06.36473″ W

1529.39

1513.16

B

C 409

40º33’10.07976″ N

105º04’46.93017″ W

1532.569

1516.664

C1

Campton

40º25’19.46764″ N

105º27’53.79807″ W

2440.161

2427.284

C1

Clarke (DESTROYED)

40º50’20.44402″ N

105º18’58.63021″ W

2014.393

2000.823

C1

Collinson Az Mk

40º22’23.84547″ N

105º29’29.77941″ W

2285.49

2272.62

B

Comstock

40º51’00.20677″ N

104º56’45.84399″ W

1785.419

1769.341

C1

Cook

40º18’18.15752″ N

105º03’35.96292″ W

1520.340

1503.603

C1

CSU (DESTROYED)

40º34’33.45418″ N

105º05’08.66359″ W

1525.73

1509.89

B

CSU 2

40º34’32.69809″ N

105º05’08.83804″ W

1525.926

1510.141

B

Dailey

40º41’05.74350″ N

105º14’14.85657″ W

1622.16

1607.73

B

Demosthenes

40º24’07.53685″ N

105º25’05.55820″ W

2135.36

2121.96

B

Disney

40º20’37.64477″ N

105º31’48.04537″ W

2454.547

2442.024

C1

Duvall

40º37’59.13607″ N

105º11’53.63851″ W

1644.521

1629.792

C1

E 137 Reset

40º47’19.36020″ N

105º11’29.06979″ W

1838.80

1824.14

B

E 20

40º23’09.47418″ N

105º11’32.50084″ W

1592.792

1577.280

C1

E 27

40º17’20.01111″ N

105º11’50.33028″ W

1664.922

1649.183

C1

E 357

40º33’58.65840″ N

105º02’25.75188″ W

1499.452

1483.308

C1

E 53

40º46’18.78304″ N

105º08’00.68772″ W

1654.983

1639.918

C1

E 7

40º25’05.46075″ N

105º11’18.66272″ W

1573.14

1557.67

B

Farren

40º18’16.41176″ N

105º09’00.60406″ W

1573.446

1557.355

C1

FC 1394

40º31’24.85370″ N

105º01’12.08510″ W

1503.303

1486.909

C1

FC 2694

40º30’06.92556″ N

105º03’29.34852″ W

1502.186

1485.987

C1

FC 923

40º36’07.30657″ N

105º01’45.08342″ W

1520.592

1504.470

C1

Feather RM 1

40º47’22.39411″ N

105º34’22.52649″ W

2515.60

2503.62

B

Finley

40º35’54.68774″ N

105º10’26.71076″ W

1660.804

1645.787

C1

FNL C

40º26’55.68980″ N

105º00’31.30126″ W

1525.8

1509.18

B

G 308

40º54’57.28480″ N

104º59’57.22037″ W

1817.587

1802.002

C1

G 402

40º23’34.42310″ N

105º04’34.34159″ W

1515.464

1499.08

B

Goering

40º41’01.37955″ N

105º07’58.11480″ W

1569.984

1554.772

C1

Greer

40º50’14.64088″ N

105º09’48.23512″ W

1814.42

1799.69

B

Guerrero

40º32’22.62735″ N

104º59’45.09076″ W

1492.8

1476.32

B

Harding

40º37’09.73323″ N

105º49’08.45011″ W

2640.90

2629.66

B

HAVEN 2014

40º27’4.91168″ N

105º27′ 2.60862″ W

2211.188

2198.348

C1

Heiden

40º47’54.46886″ N

105º04’33.61801″ W

1684.595

1669.169

C1

Hipp

40º41’47.88019″ N

105º26’40.04767″ W

1990.68

1977.79

B

Hoff

40º31’55.59036″ N

105º08’27.58732″ W

1666.241

1650.763

C1

I–25 MP 281.96

40º45’45.66118″ N

104º59’31.87692″ W

1646.23

1630.26

B

Inghram

40º57’28.13567″ N

104º58’35.06740″ W

1869.190

1853.596

C1

Johnson

40º21’33.11482″ N

104º58’57.64299″ W

1524.1

1507.11

B

K 324

40º53’02.21695″ N

105º55’53.01503″ W

2449.87

2438.78

B

Keister

40º29’14.53682″ N

105º12’21.43185″ W

1641.643

1626.576

C1

Kerr

40º29’00.98063″ N

105º01’39.84114″ W

1490.410

1473.955

C1

Kirkpatrick

40º19’20.65116″ N

105º24’54.40357″ W

2298.55

2284.93

B

L 135

40º41’01.80005″ N

105º22’48.48352″ W

1833.70

1820.35

B

L 410

40º17’26.17357″ N

105º06’11.16976″ W

1542.566

1526.09

B

Lancaster

40º33’51.05869″ N

105º13’41.01061″ W

1806.305

1791.699

C1

Lily Lake

40º18’22.99905″ N

105º32’16.95183″ W

2724.02

2711.38

B

M 356

40º42’41.01036″ N

104º56’29.71381″ W

1621.998

1605.653

C1

Macfarlane

40º21’35.05112″ N

105º16’14.57157″ W

2067.474

2052.624

C1

Miller

40º15’42.08708″ N

105º03’30.97896″ W

1522.420

1505.571

C1

Muscott

40º37’18.68997″ N

105º08’22.83527″ W

1541.966

1526.698

C1

Myhre

40º33’51.04850″ N

105º18’37.43705″ W

1903.57

1889.60

B

N 311

40º53’05.55921″ N

105º16’50.63011″ W

1990.999

1977.33

B

Nelson

40º40’06.68405″ N

105º01’11.99022″ W

1571.062

1555.041

C1

Olson

40º37’11.85668″ N

105º21’04.27031″ W

2243.985

2230.550

C1

P 135

40º41’12.92478″ N

105º18’27.64116″ W

1731.26

1717.38

B

P 137 Reset

40º57’11.96641″ N

105º20’58.13751″ W

2146.08

2133.05

B

Purdy

40º25’55.15608″ N

105º20’24.67100″ W

1878.25

1864.23

B

R 308

40º51’23.05409″ N

105º04’51.63595″ W

1728.03

1712.80

B

Ragsdale

40º52’53.17608″ N

105º08’48.31283″ W

1799.181

1784.509

C1

Railroad ET

40º48’54.99784″ N

104º58’32.69280″ W

1700.93

1684.97

B

Ranger

40º34’51.65621″ N

105º28’06.39119″ W

2522.95

2510.31

B

Roach

40º59’10.52745″ N

106º08’23.59741″ W

2699.75

2688.84

B

Rodenberger

40º39’56.35752″ N

104º57’46.33612″ W

1571.052

1554.716

C1

RP 65

40º21’00.26195″ N

105º12’31.22488″ W

1765.309

1749.850

C1

Shockley

40º31’21.72421″ N

105º15’29.10248″ W

1731.156

1716.691

C1

Smith 97

40º45’16.26813″ N

105º04’38.68448″ W

1641.29

1625.79

B

Snell

40º43’32.92509″ N

105º08’01.20866″ W

1615.453

1600.319

C1

Spencer

40º20’58.11410″ N

105º09’15.07822″ W

1571.815

1555.884

C1

Sumpter

40º38’32.52593″ N

105º17’37.13268″ W

2124.695

2110.808

C1

Thompson

40º15’40.94129″ N

105º07’57.11917″ W

1556.084

1539.733

C1

Timm

40º19’10.45282″ N

105º12’33.26228″ W

1741.860

1726.318

C1

Touslee

40º42’14.52878″ N

104º59’53.54639″ W

1591.73

1575.68

B

U 134

40º40’55.99031″ N

105º46’23.02366″ W

2390.004

2378.93

B

U 287 MP 369.85

40º49’38.81389″ N

105º14’37.19769″ W

1816.19

1802.00

B

U 311

40º56’45.11231″ N

105º15’03.96273″ W

2218.153

2204.538

C1

U 356

40º42’41.02859″ N

105º04’04.12339″ W

1610.809

1595.179

C1

V 401

40º36’25.60489″ N

105º04’32.77631″ W

1517.239

1501.447

C1

Wall I

40º33’36.67837″ N

105º52’17.91215″ W

3043.55

3032.25

B

Warwick

40º39’31.00493″ N

105º09’10.62370″ W

1600.39

1585.25

B

X 134

40º41’46.57669″ N

105º41’02.86245″ W

2326.56

2315.09

B

X 402

40º34’00.21576″ N

105º00’53.87659″ W

1490.739

1474.433

C1

Y 401

40º30’41.00149″ N

105º04’37.23253″ W

1515.457

1499.42

B