Part IIi – technical Standards

Division 13 – Special Construction

Requirements for swimming pools, fountains, aquariums, tubs and pools, controlled environment rooms, walk-in freezers, and greenhouses for CSU construction projects.

Revised – 2026.01.27

Please also refer to “Part IV – REGULATORY REQUIREMENTS” for additional requirements.

Housing and Dining Facilities (HDS) has adopted amendments for all HDS facilities. Confirm applicable standards with Project Representative on a per Project basis.

13 11 00 – Swimming Pools

A. (future)

13 12 00 – Fountains

A. (future)

13 13 00 – Aquariums

A. (future)

13 17 00 – Tubs and Pools

A. (future)

13 21 00 – Controlled Environment Rooms

A. Envelope

1. Provide insulated walls, door, and floor.

2. Provide ramp if needed.

B. Heating and Cooling

1. Do not provide air–cooled condensing units if heating and cooling infrastructure is available.

a. Example: building chilled and heating water loops

2. Heating and cooling equipment (e.g. condensing units) shall be in a location that is easy to maintain and operate.

a. Do not locate condensing units above freezer rooms.

b. Locate in a mechanical room or accessible utility chase.

3. If condensing units must be located outside, provide easy maintenance access, electric power, hydrant, low ambient operation, and hail guards.

C. HVAC Control

1. Provide Building Automation System (BAS) sensor for space, in addition to manufacturer controls

2. Room control panel can be by room manufacturer.

a. Type of chart recorder (e.g. paper or electronic) shall be determined during design.

D. Refrigerant Selection

D. Refrigerant selection shall align with Division 23 – HVAC.

1. Refer to 23 23 00 – REFRIGERANT PIPING.

E. Acceptable Products

1. Bally Refrigerated Boxes

2. Environmental Specialties

3. Or approved equal

13 21 26.16 – Walk–In Freezers

A. Refer to 13 21 00 – CONTROLLED ENVIRONMENT ROOMS.

13 34 13.13 – Greenhouses

A. General Requirements

A. All heating, cooling, plumbing, and electrical systems in greenhouse structures shall comply with respective Colorado State University Planning, Design, and Construction Standards.

B. HVAC Controls

1. Provide BAS sensors for remote monitoring of thermal conditions in addition to greenhouse manufacturer specific environmental controls.

 


End of division